How is the work progressing?

The work is progressing well. Our contractor is working flat out to reopen the bridge on Friday 2 December 2011.

Unfortunately, the bridge was in a worse condition and more frail than anticipated. When we took up the timber decking and exposed the cast iron cross girders we found substantial corrosion and many more sections needing to be cut out and replaced than predicted. 750 steelwork repairs have been completed, 40,000 litres of paint and over 1,000 tonnes of grit used during the restoration.

Testing the lights on Albert Bridge

Testing the lighting on Albert Bridge  
Albert bridge lights

 

Albert Bridge with most scaffolding removed
All the scaffolding has been removed re-veiling the refurbished bridge

 

Works on the Bridge

The strengthening and refurbishment work on the bridge is nearing completion, and the contractor is carrying out works to finish the paintwork, footways and checking all the lightings.

Albert bridge renovation 
The contractor checking the lighting and paintwork.

Prior to the bridge re-opening we need to complete the carriageway marking and Transport for London are preparing the traffic signals and at Chelsea Embankment.

We have been working with the London Borough of Wandsworth and they have rejuvenated pedestrian and cycle facilities along with resurfacing that carriageway on Albert Bridge Road whilst the bridge is closed to traffic.